Key Takeaways
- 01The Defence Industrial Strategy targets £2.5 billion more MOD spending with SMEs by May 2028 and at least 10 percent of the equipment budget on novel technologies.
- 02The Defence Investment Plan, published on 30 June 2026, commits £298 billion over four years, but UK Defence Innovation receives £1.6 billion against £11.1 billion for munitions. Entry points are specific.
- 03Before the plan appeared, techUK's May 2026 survey of 45 suppliers found 87 percent had faced funding delays or reductions and 73 percent a contract suspension or cancellation.
- 04The strategy aims to cut time to contract from six years to two on major platforms, yet the plan records that 47 of 49 major projects were delayed or over budget.
- 05Plan for two timelines: a fast policy cycle that opens doors now and a slow buying culture that pays later. Fund the gap, and aim where money is already committed.
The Karter McKinley perspective
Plan for the policy's timeline and the buyer'sKarter McKinley
We hold that the Defence Industrial Strategy is a sincere invitation and an incomplete guarantee. Targets for SME spending, novel technology and faster contracting signal that ministers want new entrants, and the commitment of £298 billion in the Defence Investment Plan gives the signal weight. But buying behaviour changes through people, processes and incentives, which move more slowly than policy documents. A new supplier should therefore expect the door to be open and the corridor behind it to be long.
The practical answer is to build a plan with two clocks. The policy clock sets when programmes, funds and targets appear; the buyer clock sets when contracts are signed and invoices paid. Firms that survive the gap between them do three things: choose segments where money is already committed, secure a route through a prime or an innovation programme, and hold enough cash to bridge a delay of a year or more. Those that rely on the policy clock alone are the ones the surveys describe as struggling.
The UK is spending more on defence, and the headline is now backed by a plan
For a firm new to defence, the first question is whether the market is real. The answer is yes, though its shape is uneven. Governments across Europe are raising budgets, the United Kingdom has committed to higher spending through 2035, and in June 2026 it published the long-awaited investment plan that allocates the money. The opportunity is therefore less about whether demand exists than about where it sits and when it turns into contracts.
SIPRI reports that world military expenditure reached $2,887 billion in 2025, an increase of 2.9 per cent in real terms, with a 14 per cent rise in Europe to $864 billion. The UK, by contrast, decreased spending by 2.0 per cent to $89.0 billion between 2024 and 2025. NATO's June 2025 estimates put UK defence spending at 2.14 percent of real GDP in 2014 and 2.40 percent in 2025, the latter an estimate.
The Defence Investment Plan changes the trajectory. It states that spending will reach 2.7 percent of GDP by the end of the decade, up from 2.3 percent when the government took office, and that the UK has committed to its allies to reach 3.5 percent by 2035. Clifford Chance reports that the plan was published on 30 June 2026 and confirms £298 billion over the next four years. For suppliers, the money is moving from aspiration to allocation.
The implication for a chief executive is that defence is a structurally growing market, but one in which the UK is catching up rather than leading. That affects pricing power and timing. Budgets will rise, yet competition for them will intensify as incumbents, primes and newcomers all target the same priority areas. The sensible stance is to treat defence as a multi-year strategic option and size the investment accordingly.
Check which share of your addressable market depends on UK defence compared with allied customers. UK buyers will not be the only source of demand, and many capabilities, from autonomy to secure communications, are being procured across NATO members. A UK qualification and reference can be a gateway to export markets, and the strategy itself pairs domestic reform with export financing. Plan the sequence so that UK success supports, rather than replaces, wider market development.
The strategy invites newcomers with explicit targets
The Defence Industrial Strategy 2025 is unusually specific about new entrants. It does not merely express goodwill; it sets numerical targets that the Ministry of Defence can be held to. For a company with no defence history, those targets matter because they create internal incentives for buyers to look beyond the usual suppliers, and because they supply a vocabulary, SMEs and novel technology, that can be used when approaching programme offices.
The strategy introduces a target to increase MOD spending with SMEs by £2.5 billion by May 2028, and commits the Ministry to spend at least 10 percent of its equipment procurement budget on novel technologies. It also ringfences an annual UK Defence Innovation budget of at least £400 million. Government has said only 4 percent of this spending went to SMEs in 2023-24 and that support is a vote of confidence in the prospects of up to 12,000 SMEs.
Exhibit 1
UK defence spending has crept back above 2 percent of GDP
UK defence expenditure as a share of real GDP, % (2024 and 2025 are NATO estimates)
A further signal came with a new £20 million fund offering accelerated contracts to innovative UK start-ups with little previous MOD engagement, which the government cited when pointing to existing measures for smaller firms. In total, the Ministry spent £28.8 billion with UK industry in 2023/24, so the SME target is meaningful but modest in relation to the whole. It is designed to move the margin, not to restructure the supplier base overnight.
The implication is that newcomers are a priority at the margin, which is where a smaller or less established firm can win. The targets are most useful when a supplier can offer something buyers lack: a technology the primes cannot easily develop, speed of delivery or a price point that fits experimental budgets. Generic capability offers, however capable, will not benefit from the targets because they do not map to a specific programme need.
Translate the targets into your outreach. Cite the SME and novel-technology objectives in conversations with programme officers and prime contractors, because both are measured against them. Ask directly which commercial route, innovation programme, framework or prime subcontract, best fits your technology. And monitor the progress of the targets themselves: if reported SME spending is not moving, expect the Ministry to push harder on intermediaries and routes that count towards the objective.
There is also a reporting dimension. Targets that are measured tend to be managed, and the Ministry will want to show progress against the SME objective in the years before May 2028. That gives smaller suppliers some negotiating leverage with primes, who are under pressure to demonstrate how much of their supply chain value reaches smaller firms. A newcomer that can document its SME status and its contribution to a programme may find that primes are more receptive than the historic pattern would imply.
The Defence Investment Plan shows where the money actually goes
Strategy documents tell suppliers what the government wants; the investment plan tells them what it has funded. For a company deciding where to focus, the second is far more valuable. A £298 billion four-year envelope is vast, but it is concentrated in a small number of large lines, and the opportunities for newcomers vary significantly by line. Reading the allocation is the starting point of any entry plan.
The plan allocates over £20 billion to multiply the Army's lethality through autonomous systems, £11.1 billion to munitions and weapons to increase UK stockpiles, over £5 billion to autonomous systems and £1.6 billion to UK Defence Innovation over the next four years. It also records that since July 2024 the government has signed over 1,400 major defence contracts, with 94 percent of the total value going to UK-based firms.
Exhibit 2
The UK is a mid-sized military spender in a market dominated by the United States and China
Military expenditure, 2025, $bn
The pattern is instructive. Autonomy, munitions and drones are large and funded, and they are fields where small, fast-moving firms can supply components, software, sensors and manufacturing capacity into larger programmes. By contrast, the dedicated innovation line is small relative to the whole, by our arithmetic about half of one per cent of the total. Innovation money is a valuable entry route but not the main market. Most newcomer revenue will come through programme supply chains.
A newcomer should therefore decide early whether it is an innovator, seeking grants and early contracts, or a supplier, seeking a role in a funded programme. The routes, requirements and timescales differ. Innovation funding rewards novelty and tolerates risk; programme supply rewards reliability and compliance. Some firms start with the first to build credibility and move to the second for scale, and that sequence can be planned from the beginning.
Map your product against the funded lines. For each, identify the prime contractors, the programme offices and the likely subsystems. Then test whether your offer solves a problem that appears in the programme's own documents, such as capacity shortages in energetics or integration challenges in autonomy. A proposal framed as a solution to a named programme problem has a far better chance than one that merely describes technology and hopes for a use.
One more observation concerns timing within the four-year window. Large programme lines are typically contracted in tranches, with early awards going to established suppliers and later lower-tier opportunities following as designs mature. A newcomer approaching a prime at the point when subsystems are being specified has more influence than one arriving after the architecture is fixed. Following programme milestones closely, through published notices and prime contractor engagement events, is therefore more productive than generic market watching.
Procurement reform is promised on a timescale the buying culture may not match
The strategy's most important commitments for newcomers concern how the Ministry buys, not how much. Long procurement timelines are the main reason small firms avoid defence: they cannot fund years of bid cost and delay. If time to contract falls materially, the economics of entry change. The question is whether the reform will be delivered, and on what schedule, because reform of buying behaviour is slow.
The Defence Industrial Strategy sets a timescale target to go from an average of six to two years to contract for major platforms, and from three to one year for modular upgrades, with three-month cycles for rapid commercial exploitation. Yet the Defence Investment Plan itself records that 47 out of 49 major projects were delayed or over budget.
Exhibit 3
Innovation is a small line in a large plan: autonomy and munitions take the bulk
Selected Defence Investment Plan commitments over four years, £bn ('over' or 'at least' for several lines)
The National Audit Office's 2020 review, which pre-dates the strategy and should be read as historical context, found average forecast delays of 12 months to initial operating capability and 26 months to full operating capability. The numbers differ in scope, but the direction is consistent: delay has been a chronic feature. Reform targets are credible as ambitions, and the scale of the gap between aspiration and history is a reason for a supplier to plan conservatively.
The implication for a new entrant is that rapid routes will matter more than the headline platform timescale. The three-month cycles intended for rapid commercial exploitation, and the innovation programmes, are where faster decisions are likely to occur first. Major platform contracts will remain slow for years, and a business plan that assumes the six-to-two-year target will be met in time to rescue cash flow is relying on a hope.
Build your plan around the faster routes, and treat any acceleration in major contracting as upside. Ask each potential buyer for a realistic timeline from first meeting to contract and to first payment, and compare it with what the policy says. Where the answer is longer, budget for that, and negotiate payment terms, milestones and advances that protect your cash. A supplier that can survive the slower timeline is the one still standing when reform arrives.
Suppliers are already feeling the strain of uncertainty
The experience of existing suppliers is the best guide to what a newcomer will meet. The investment plan arrived late, and during the wait many suppliers reported disruption. This matters for entrants for two reasons: it shows how the system behaves under fiscal and administrative pressure, and it shows which kinds of firm were hit hardest. Both help a newcomer decide how much risk to take and what protections to build.
techUK, the technology trade body, surveyed 45 defence technology suppliers in May 2026, before the plan was published. It found that 93 percent were reassessing investment or recruitment decisions, 87 percent had experienced funding delays or reductions in the last six months and 73 percent a contract suspension or cancellation. In addition, 67 percent said SMEs in their supply chain had been directly impacted, 47 percent were awaiting a contract extension and 73 percent said the market had declined since the Strategic Defence Review.
Exhibit 4
Suppliers reported widespread disruption before the investment plan was published
Share of 45 UK defence technology suppliers reporting each, May 2026, % (trade-body survey)
There are caveats. This is a trade-body survey of a small sample, 18 small, 12 medium and 15 large firms, and it reflects the views of an interest group. It predates the Defence Investment Plan, so it does not show whether conditions have improved since. But the pattern, delays falling heaviest on smaller firms and on contract extensions, is consistent with what the government's own SME statistics suggest, and it is precisely what a newcomer needs to plan for.
The implication is that cash resilience is the primary strategic variable for a new defence supplier. Technical excellence will not offset a contract delayed by two quarters if the firm has no reserves. Newcomers also face a particular risk: they have fewer existing contracts to cushion a delay and less knowledge of whom to call. Treat the survey as a stress test and ask whether your plan would survive the same experience.
Build the plan on conservative assumptions. Hold enough cash or committed funding to cover a delay of at least two quarters beyond the buyer's stated timeline. Diversify across customers, including commercial and export, so no single decision can stall the business. Maintain relationships with several programme offices and primes. And ask direct questions about contract extension status and payment practice during due diligence on any prime you intend to supply.
New suppliers win by solving a programme problem, not by selling a product
Defence buyers rarely purchase products in isolation. They procure capabilities that must integrate with existing platforms, meet security and assurance requirements, and be supportable for decades. A product that is excellent in a commercial setting may fail to enter because it does not fit those constraints. Successful newcomers recognise this and frame their offer as a contribution to a capability, with a clear understanding of the buyer's operational and procurement context.
The structure of recent contracting reinforces the point. The government says it has signed over 1,400 major defence contracts since July 2024, with 94 percent of the value going to UK-based firms, and the plan calls for six new energetics factories by 2030. These signals suggest strong demand for UK-based capacity, particularly in munitions and associated manufacturing, where a newcomer with relevant industrial skills may be valued more for capability than for defence pedigree.
Exhibit 5
Routes into UK defence for firms new to the sector
| Route | Best suited to | Main constraint |
|---|---|---|
| Innovation programmes and funds | Novel technology, small teams | Small budgets; scaling needs a second route |
| Subcontract to a prime | Component, software and manufacturing capacity | Dependence on the prime's timetable and terms |
| Munitions and energetics supply chain | Industrial capacity and process skills | Safety, compliance and capital requirements |
| Partnership or joint bid | Firms needing assurance and past-performance credentials | IP, exclusivity and revenue-sharing negotiations |
| Export-led entry via allies | Products proven in commercial markets | Export controls and long sales cycles |
For a chief executive the implication is that defence readiness is a programme in its own right. It covers compliance with security requirements, understanding of assurance processes, a credible quality system and the ability to support a product through life. These take time and money to build, and they are what primes assess before bringing a new supplier into a bid. Firms should treat them as an investment in access.
Choose a narrow entry point and build depth rather than breadth. Identify two or three programmes where your capability is clearly relevant, learn their documents and language, and approach primes with a specific proposal for a specific need. Offer evidence: test data, pilots and references from commercial customers. Where gaps exist, such as security clearance, certifications or defence-specific quality standards, plan for their acquisition and be candid about the timeline.
Consider partnerships. A newcomer can often enter faster as a subcontractor or technology partner to an established firm than as a prime. The arrangement gives the buyer a known counterparty and gives the newcomer access to compliance infrastructure it would otherwise have to build. Negotiate carefully on intellectual property, exclusivity and route to market, so the relationship remains a stepping stone and does not become a ceiling on growth.
Finally, think about reputation as an asset that compounds. In a small, closely connected sector, a supplier that delivers a modest first contract on time and to specification becomes known to programme officers and primes quickly, and that reputation travels. The reverse is also true. Overpromising on a first bid in order to win entry can damage standing for years, so it is better to propose a smaller scope that can be delivered well and then expand.
Plan for two timelines: a fast policy cycle and a slow buying cycle
The policy environment has moved quickly: a Strategic Defence Review in 2025, an industrial strategy later that year and an investment plan in mid-2026. The buying environment is moving more slowly, constrained by the capacity of commercial teams, the sequencing of programmes and the habits of risk-averse organisations. A newcomer who plans according to the policy cycle will find that cash arrives later than the announcements suggest.
The techUK survey illustrates the point: respondents pointed to the wider financial climate within the MOD, delays to defence reform and the appointment of senior decision-makers, and a shortage of commercial officers to get contracts onto paper. These are capacity constraints that policy announcements do not immediately solve. The plan's publication removes one source of uncertainty, but others, such as commercial staffing, remain and will govern the pace of contract signature.
Exhibit 6
Where to aim: fit with funded priorities against time to first revenue
The implication is that a sensible entry strategy has stages with gates linked to evidence of buyer behaviour, not policy statements. Stage one is to qualify: understand requirements, secure introductions, build compliance. Stage two is to demonstrate: pilots, trials or small contracts. Stage three is to scale: framework positions or programme roles. Each stage needs funding that does not depend on the next, so a delay does not become a failure.
Set explicit gates. For example, do not commit to capacity investment until a programme-level commitment exists in writing. Do not hire a defence sales team before at least one prime has asked for a proposal. Keep a running record of the difference between announced and actual timelines in your own experience, and use it to calibrate future plans. After two or three cycles it will be a more reliable guide than any published target.
Finally, remember that policy can also move against you. Budgets are subject to fiscal pressure, priorities shift as threats evolve and ministers change. A supplier that has positioned itself in areas of enduring need, such as munitions capacity, autonomy and digital infrastructure, and that has maintained commercial customers alongside defence, is better placed than one that has staked everything on a single programme. The strategy is a tailwind, not a safeguard.
Questions for the leadership team
- Which funded Defence Investment Plan lines does our technology map to, and which prime owns each?
- Are we pursuing the innovation route, the supply-chain route or both, and in what sequence?
- Do we have at least two quarters of cash beyond the buyer's stated contract timeline?
- Can we show test data, pilots and references that address a named programme problem?
- What security, quality and assurance credentials do we lack, and when will we have them?
- Have we diversified across customers so one delayed decision cannot stall the business?
- What gates link spending to evidence of buyer behaviour rather than policy announcements?
- Which partnership gives us compliance infrastructure without capping our growth?
How Karter McKinley helps
Our Strategy & Transformation work helps firms new to defence assess which funded programmes fit their capabilities, design a staged entry plan with cash gates, and prepare the evidence and partnerships that primes and programme offices look for. We support the planning process; we do not claim relationships with the Ministry of Defence or any contractor.
Turning strategy into results? Let's talk.
Book a free 30-minute introduction call with our team. No obligation.
Frequently asked questions
It is the government's plan to make defence an engine for economic growth, published in 2025. It sets targets to raise MOD spending with SMEs by £2.5 billion by May 2028, spend at least 10 percent of the equipment budget on novel technologies, ringfence at least £400 million a year for UK Defence Innovation and cut time to contract.
It creates explicit incentives for buyers to use SMEs, including the £2.5 billion spending target and a £20 million fund for start-ups with little MOD engagement. The government said only 4 percent of this defence spending went to SMEs in 2023-24. In practice, benefit depends on matching a specific programme need and surviving contracting delays.
The Defence Investment Plan, published on 30 June 2026, allocates £298 billion of investment over four years, including over £20 billion for autonomous systems to multiply the Army's lethality, £11.1 billion for munitions and weapons, and £1.6 billion for UK Defence Innovation. It follows the 2025 Strategic Defence Review.
Choose a narrow entry point where a funded programme has a clear problem you can solve, then enter via an innovation programme, a prime's supply chain or a partnership. Prepare compliance credentials early, offer evidence from commercial use and hold enough cash to cover contracting delays. Treat defence readiness as an investment programme.
NATO's June 2025 estimates put UK defence expenditure at 2.40 percent of real GDP in 2025. The Defence Investment Plan states that spending will reach 2.7 percent of GDP by the end of the decade, and the UK has committed to its allies to reach 3.5 percent by 2035.
- UK Ministry of Defence — Defence Industrial Strategy 2025 two-pager
- UK Government — Defence Industrial Strategy 2025: Making Defence an Engine for Growth
- GOV.UK — New measures to boost small businesses benefitting from UK's defence investment
- UK Government — The Defence Investment Plan (June 2026)
- Clifford Chance — The UK Defence Investment Plan: what to watch
- NATO — Defence Expenditure of NATO Countries (2014-2025)
- SIPRI — Global military spending surges (April 2026)
- techUK — Survey of defence tech suppliers (May 2026)
- UK Defence Journal — Defence SME action plan to follow Defence Investment Plan
- National Audit Office — Defence capabilities: delivering what was promised (2020)